Queensland’s new Construction Productivity Code: what you need to know

Shae McCartney and Elizabeth Furfaro
19 Nov 2026
5 minutes

The Queensland Construction Productivity Code 2026 took effect on 17 November 2026, less than three weeks after the CFMEU Commission of Inquiry called for urgent action. For anyone bidding for, delivering or procuring major State-funded construction work in Queensland, compliance with this Code is now a condition of access to the government pipeline.

Key actions at a glance

If you bid for, deliver or procure Queensland Government-funded construction work valued at more than $150 million, you should now:

Contractors and subcontractors:

  • audit your enterprise agreements (and those of related entities) against the Code’s list of inconsistent arrangements, and be ready to disclose and explain any affected clauses in your WRMP;

  • build your WRMP capability now, so you can give the required written commitment at the expression of interest stage and a full WRMP when requested;

  • update subcontract templates to pass down Code warranties, DSDIP access rights and reporting obligations, and put 24-hour reporting procedures in place;

Government agencies:

  • Identify which projects are captured, update procurement documents across all delivery models, and build WRMP assessment, DSDIP referral and exemption procedures into evaluation and contract management; and

Everyone:

  • Watch for the model WRMP and model contract clauses, the Commission’s Final Report and developments at the federal level (see “Further change” below).

More detail on each step is set out under “What clients need to do” below.

Executive summary

The Queensland Government has introduced the Queensland Construction Productivity Code 2026 (the Code), together with a new compliance function within the Department of State Development, Infrastructure and Planning (DSDIP). These actions arise from the two recommendations of the Interim Report of the Commission of Inquiry into the CFMEU and Misconduct in the Construction Industry, delivered by Commissioner Stuart Wood AM KC on 30 October 2026.

The Commissioner described an “urgent and pressing need” for a code and regulator after more than 50 hearing days and evidence from over 80 witnesses. The Interim Report includes the Commissioner’s estimate that the former Best Practice Industry Conditions (BPIC) policy added around 20% to the cost of government infrastructure projects. With a State capital pipeline of some $119 billion, including the Brisbane 2032 venue program, the Government has made productivity, lawful conduct and value for money its central construction procurement priorities.

In short, the Code:

  • applies to new Queensland Government-funded construction work valued at more than $150 million, where the expression of interest or request for tender is issued on or after 17 November 2026;

  • binds Queensland Government client agencies, principal contractors, subcontractors and consultants who take part in on-site activities, to the extent the relevant requirements relate to their role, work, contractual influence and practical control;

  • requires a Workplace Relations Management Plan (WRMP) before contract award, contractual warranties of compliance and audit access for DSDIP;

  • targets restrictive workplace arrangements commonly found in construction enterprise agreements, and imposes 24-hour reporting obligations; and

  • makes ongoing compliance a condition of continued access to Government work.

The Code does not:

  • apply to privately funded work;

  • apply to construction work undertaken by a Queensland Government department, agency or government-owned or government-operated delivery entity using its own workforce (including RoadTek and QBuild), or by local councils engaged to undertake works on behalf of the Queensland Government; or

  • override, displace or alter any requirements under the Fair Work Act 2009 (Cth).

Where the Code has come from

The Code is not a new idea. Queensland had Implementation Guidelines to its Code of Practice for the Building and Construction Industry, supported by a Building and Construction Compliance Branch, between 2013 and 2015. Those Guidelines were removed in 2015 and, over time, the BPIC policy was introduced. The Commission’s Interim Report examined the operation of the BPIC policy across the contracting chain.

The Commission’s Interim Report attached a “Recommended Code” closely modelled on the 2013 Guidelines, with a series of additions drawn from the evidence. The Government’s Code adopts much of that model, but differs from it in several commercially significant respects. It also sits alongside the Queensland Procurement Policy 2026 (QPP) and the Supplier Code of Conduct 2026, which prevail over the Code if there is any inconsistency.

Key changes to be aware of

New obligations on contractors, subcontractors and employers

Principal contractors carry the heaviest load under the Code requirements. They must:

  • build the Code into tender and contract documents, including legally enforceable warranties of compliance from subcontractors, consultants and related entities;

  • actively manage compliance with the Code by subcontractors, consultants and related entities;

  • give DSDIP access to inspect work and records and to interview people;

  • use all reasonable efforts to ensure that subcontractors comply, and actively monitor how they meet their workplace relations obligations;

  • prepare, comply with and act consistently with the tender response and the WRMP, which must cover labour sourcing, workplace arrangements, subcontractor management, industrial-relations risks, disputes, site access, productivity and delivery within budget and on time, among other things;

  • report threatened, possible, likely or actual unlawful industrial conduct, Code breaches, industrial action and disputes that may affect cost or programme to the DSDIP within 24 hours, then give regular updates and lost-time data; and

  • take reasonable steps, including legal remedies where available, to prevent or end unprotected industrial action. Failing to pursue appropriate remedies may itself be a breach.

Subcontractors must comply with the Code as far as reasonably practical, from the time they tender, but only for requirements relevant to their work or services. They must give a warranty to comply with the Code and allow the DSDIP access to inspect any relevant work, records, documents and people, meet all legal obligations (including to avoid sham contracting and arrangements to avoid strike pay obligations), meet their WHS duties, and report suspected breaches to DSDIP within 24 hours.

The Code’s definition of “reasonable” considers a party’s position in the contracting chain, its practical ability to influence conduct and market capacity.

All parties subject to the Code must comply with and promote applicable awards, agreements and orders, and must not enter into unregistered written agreements with third parties in relation to industrial matters. They must also avoid a long list of practices said to undermine freedom of association, including “no ticket, no start” practices, union-administered inductions without site management oversight, non-working delegates, union signage required on site and providing new starters’ details to unions other than as required by law. No payments may be made to unions or their officials, directly or indirectly, for any reason. All parties to the Code must also maintain confidentiality in connection with commercial issues and report any suspected non-compliance with the Code to DSDIP.

Client agency responsibilities

Government agencies must ensure any party engaged to undertake publicly funded construction work complies with the Code. Key responsibilities include:

  • establishing internal coordination procedures for management of Code matters that relate to the client agency, such as reporting requirements and exemption requests;

  • embedding the Code in relevant procurement processes, ensuring that expressions of interest, tenders and contracts clearly state Code requirements and compliance is part of the agency’s contract-management systems;

  • ensuring that relevant contracts require the principal contractor and subcontractors to comply with the Code as well as allow the DSDIP to inspect works and records and interview relevant people;

  • refer notifications received regarding unlawful industrial conduct, disputes, industrial action, or work health and safety matters that could affect cost, timing or related contracts to the DSDIP in a timely manner;

  • take appropriate compliance action where a breach of the Code is confirmed; and

  • consider any exemption requests robustly and document the reasons fully.

Enterprise agreements and workplace arrangements

The Code has a strong focus on ensuring that workplace arrangements that are inconsistent with or otherwise are aimed at circumventing the Code are not entered into. The Code defines “workplace arrangement” broadly to cover any agreement, understanding, practice or policy, whether written or not. Arrangements that are inconsistent with the Code include those that:

  • set employee ratios or restrict the source or type of labour (including casuals and labour hire), or require union consultation or approval over labour engagement;

  • provide for one-in-all-in overtime, last on, first off redundancy selection or restrictions on all-in payments;

  • prevent an employer from substituting a rostered day off, so that work cannot be performed every day;

  • relax statutory right of entry requirements or allow non-parties to monitor the agreement;

  • provide standing paid time off for union activities beyond award or legislative entitlements;

  • require above-minimum contributions to industry superannuation, redundancy or income protection funds, unless each employer chooses to make them; or

  • provide for a site allowance without a specified amount or an objective and predictable method for calculating it.

Importantly, an approved enterprise agreement containing one of these provisions does not automatically disqualify a tenderer. Instead, the tenderer must disclose the provision in its WRMP, and in its compliance declarations for itself and its related entities, and explain how it will manage any impact on cost, productivity and delivery.

Compliance and enforcement

DSDIP is responsible for monitoring compliance with the construction-specific requirements of the Code. It will work alongside the Procurement Assurance Branch, which continues to administer the QPP and the Supplier Code of Conduct. DSDIP’s functions include reviewing tender and contract documents, investigating tenderers’ current workplace compliance, conducting audits and site inspections on its own initiative, and reporting proven breaches to the Minister for Industrial Relations with recommended sanctions.

Suppliers may face the consequences available under the Procurement Assurance Model framework (which is part of the QPP), and breaches may be referred to industry associations, regulators or law enforcement. The Code states plainly that continued access to Government procurement depends on maintaining compliance. In its first phase, the new function will focus on education and awareness.

Client agencies are also accountable. Proven breaches by an agency are reported to its Chief Executive, who must advise DSDIP of the remedial action taken.

Commencement, transition and exemptions

Commencement: the Code applies to work released to market on and after 17 November 2026.

  • Carve-outs: procurements already in market, existing contracts (including variations, extensions and options), projects that have passed a prescribed commitment milestone, and rolling upgrade or maintenance programs are excluded. Work carried out by government delivery entities using their own workforce, such as QBuild and RoadTek, and by local councils working for the State, is also excluded.

  • Opt-in: a client agency’s Minister may seek the Responsible Minister’s approval to apply the Code to an existing procurement, an existing contract or a contract below $150 million.

  • Exemptions: these are available only in exceptional circumstances and in the public interest. Requests must be certified by the agency Chief Executive, assessed by DSDIP and decided by the Responsible Minister, and are recorded on a central register.

  • Practice Directions: DSDIP or the Minister may issue guidance on how the Code is interpreted or applied, but cannot override an industrial instrument or the Fair Work Act.

  • Model WRMP: the Office of Industrial Relations has said a model WRMP will be released shortly.

What clients need to do

Private contractors and subcontractors tendering for Queensland Government-funded projects

  1. Audit your enterprise agreements now: Map every agreement across your group and related entities against the Code’s list of inconsistent arrangements. Identify the clauses you will need to disclose and prepare a credible explanation of how you will manage their impact on cost and programme.

  2. Prepare for the WRMP: At expression of interest or initial tender stage, give the written commitment the Code requires and be ready to provide a full WRMP when requested. Build a WRMP capability that covers every required matter, including labour sourcing and hire, subcontractor management, plant and equipment utilisation, industrial relations risk, site access, productivity, cost control and the recruitment and retention of women.

  3. Update your subcontract templates: Pass down Code warranties, DSDIP access consents, reporting obligations and WRMP compliance, and decide how you will monitor subcontractor compliance in practice. Commit to re-reviewing these templates once the model contract clauses are released to ensure compliance.

  4. Stand up 24-hour reporting: Put in place procedures to notify DSDIP and the client agency of disputes, industrial action, unlawful conduct, suspected breaches and lost time, with clear internal escalation paths.

  5. Review site practices: Check inductions, signage, delegate arrangements, right of entry handling and any dealings with unions or union-controlled funds against the freedom of association requirements.

  6. Assemble your track record: Gather evidence of safe, on-time and on-budget delivery and your WHS systems, together with a remediation narrative for any past shortfalls, and confirm that your prequalification information is current.

Queensland Government agencies as project owners and funders

  1. Map out your projects package by package: Identify which projects and packages will be captured by the threshold of the Code, which fall within any carve-outs, and any existing procurements that may warrant Ministerial opt-in.

  2. Clarify interfaces with own-workforce delivery: Works delivered by a government department, agency or government-owned or government-operated delivery entity using its own workforce are excluded, but contracted works on the same sites are not. Make clear in interface and access arrangements who is responsible for Code compliance, reporting and DSDIP access at shared work sites.

  3. Establish internal procedures: Set up procedures for managing Code matters, including nominating accountable officers, receiving and referring notifications to DSDIP, handling exemption requests and acting on DSDIP findings. Ensure project and commercial teams understand the WRMP and assurance requirements.

  4. Update procurement documents: Expressions of interest, tenders and contracts for in-scope projects must clearly set out the Code requirements, including enforceable warranties and DSDIP access rights, across all delivery models (including PPPs, alliances, managing contractor and construction management arrangements). Undertake a full review of all procurement documents and update them to ensure compliance with the new requirements.

  5. Build WRMP assessment into evaluation: You must be satisfied that the WRMP complies before awarding the contract. Plan how you will assess disclosed enterprise agreement provisions consistently with value for money and fair competition under the QPP.

  6. Plan for critical works and shutdowns: Industrial action or a dispute during periods of possession or critical works can have an outsized effect on cost and programme. Require contractors’ WRMPs to include possession-specific dispute escalation, reporting and contingency plans, and the steps they will take to prevent, manage or end unprotected industrial action, and agree in advance how notifications will reach your project team and DSDIP during a critical works period.

  7. Manage contracts actively: Monitor contractors’ compliance, refer notifications to DSDIP promptly and document the action you take after a confirmed breach.

  8. Approach exemptions with care: Applications require full reasons, a risk analysis and Chief Executive certification, and decisions will be recorded centrally.

Further change

Further change is also likely, with the Commission’s Final Report due by 3 December 2027. The Commissioner has flagged further issues for consideration, including whether to extend the Code to private work.

At the federal level, there is currently no Commonwealth equivalent of the Code. The Australian Building and Construction Commission was abolished in February 2023, and the Coalition’s Building and Construction Industry (Restoring Integrity and Reducing Building Costs) Bills 2024, which sought to restore it, have lapsed. On 1 May 2026, the Commonwealth Government announced that it would consult on potential standards for the construction industry, aimed at ensuring that government financial arrangements drive quality, productivity and lawful behaviour. A discussion paper was released on 21 August 2026 and submissions have now closed, but no decisions have yet been taken on the design, scope or implementation of any standards. [Insert details of the federal Bill currently before Parliament, if a specific Bill is intended.

If you would like to discuss how the Code affects your business or your upcoming projects, please contact us.

Be the first to know

Legal updates and articles on the topics that matter to you, sent as they happen.

Subscribe
Disclaimer
Clayton Utz communications are intended to provide commentary and general information. They should not be relied upon as legal advice. Formal legal advice should be sought in particular transactions or on matters of interest arising from this communication. Persons listed may not be admitted in all States and Territories.