24 November 2008
Key Points:
A failure to respond to payment claims and payment disputes under Security for Payment Legislation can give rise to significant liabilities and change who bears the solvency risk during payment disputes.
There is an old saying that "he who writes the cheques, calls the tune". Whoever came up with that expression probably had the building and construction industry in mind at the time.
Historically, because owners or head contractors (in the case of subcontracts) were the ones who wrote the cheques, they were usually in a better bargaining position if disputes about payment entitlements arise. However, times have changed. While the above saying still holds true, the advent of Security for Payment (SOP) legislation[1] in most states has shifted the balance of power from those who write the cheques to those seeking to receive them.
The legislation, introduced progressively around most of Australia since 1999, allows for private adjudication to accelerate an interim resolution of all payment disputes as the project proceeds, leaving the parties to later follow other dispute resolution procedures to adjust any interim decision should they so choose. The statistics show adjudication can be very effective at forcing early payment, potentially requiring owners / contractors to pay much earlier in the dispute process and leaving them with the task of recovering money they have historically retained in the event of a dispute.
Unfortunately, the adjudication scheme is not uniform across all states (and in South Australia and Tasmania currently does not exist at all), with the result that the SOP legislation is more widely used in some states than others. That lack of consistency complicates the management of security of payment issues at a national level and can lead to participants in the process being caught out to their detriment.
Broadly, there are two SOP legislative models in operation in Australia , though within each model there are variances between jurisdictions:
(a) The Eastern Model adopted by New South Wales, Victoria and Queensland (and proposed to be adopted by South Australia); and
(b) The Western Model adopted by Western Australia and Northern Territory.
Of the two models, it is the Eastern Model that owners and contractors must be the most alert to, because of the serious consequences which can flow if the recipient of a payment claim made under a relevant SOP Act does not take appropriate steps within a very tight timeframe.
It is the location of the construction site that determines which of the various SOP Acts apply. If the site is in Queensland, it is the Queensland Act that applies. If it is in WA, it is the WA Act that applies, and so on.
All of the SOP Acts apply to a very wide range of contracts connected with virtually any type of building and construction work (but generally excluding mining).
Eastern Model
The SOP Acts adopting the Eastern Model create a scheme for making payment claims under the Act which operates in addition to, and parallel with, any contractual scheme. Only the person who carries out the construction work or supplies the goods or services can make claims under the statutory process. An owner cannot make a payment claim against its head contractor or head contractor against its subcontractor.
The key feature for recognising a claim made under an SOP Act is that the claim must expressly state that it is a claim made under the relevant Act. Claimants often try to make this notation as insignificant as possible in the hope that the respondent will not take the timely and formal steps needed in response in order to fully participate in any adjudication process which follows.
To respond to a statutory payment claim a respondent must issue a Payment Schedule within 10 business days (or earlier if a shorter timeframe is required by the relevant contract) stating the amount (if any) that the respondent proposes to pay and fully setting out the reasons why there is any reduction from the amount claimed. If this is not done properly, there can be serious consequences for the respondent if there is a further dispute about the payment:
A claimant who is dissatisfied with the amount stated in a Payment Schedule or if there is no Payment Schedule can choose to pursue its claim in adjudication (discussed further below).
Western Model
The Western Model differs to the extent that it does not provide for the statutory payment claim process. It leaves payment claims by either party against the other to the process stated in the contract or, if there is no process, the SOP Acts imply a process into the contract. If that process gives rise to a payment dispute (whether that dispute be about claims by the contractor against the owner or vice versa), either party can refer the payment dispute to adjudication (discussed next)
Adjudication - Eastern and Western Models
All the SOP Acts establish an adjudication process which is roughly the same in structure, though there are some variances with some elements and the timing of steps:
After the adjudicated amount is paid, it is the respondent who has the inconvenience and solvency risk of pursuing the respondent for the repayment of any amount which the respondent believes the adjudicator awarded in error. And, if the money was sought to be withheld for what the respondent legitimately believed was defective or incomplete work, the making of the payment will have removed any leverage the respondent had to have that work properly completed.
For these reasons it is important that payment claims delivered under SOP legislation (in the case of NSW, Vic and Qld) and payment disputes (in the case of WA and NT) are recognised quickly and dealt with appropriately so that rights are not needlessly lost.
[1] NSW: Building and Construction industry Security of Payment Act 1999
For further information, please contact Frazer Moss and Robert Backstrom.