21 December 2007
Key Points:
Although the final version of the NSW PPP Commercial Principles are similar to Victoria’s, there are key differences in the respective termination regimes.
In order for a PPP social infrastructure project to be bankable, a project agreement must deal comprehensively with the consequences of early termination. The release of the final version of the NSW Government’s "Working with Government: Risk Allocation and Commercial Principles" ("NSW Commercial Principles") reveals significant areas of commonality between NSW and Victoria on how they deal with the vexed issue of termination of a project agreement.
There are, however, a number of differences in the operation of the termination regimes in NSW when compared with Victoria. This article will highlight a number of those differences, as well as examine the method of calculation of termination payments provided for under the Victorian and NSW Commercial Principles[1].
Structure of the Termination regime
In general terms, Government may terminate a project agreement upon occurrence of a Termination Event or, in some cases, a Force Majeure Event. Government may also voluntarily terminate a project agreement (subject to payment of a termination payment), while the private party to a project agreement can terminate in the event of State Default.
Default Termination
Both Victoria and NSW share a general two tier termination regime in the event of default by the private party.
The first tier covers the more serious defaults which do not have cure rights, called Termination Events.
The second are those which do have cure rights are Events of Default. NSW also has a third tier of termination events called Persistent Breaches.
Differences in the Termination Event regimes
Termination Events are events which give rise to an immediate right for Government to terminate the Project Agreement – ie. there is no opportunity to cure. The list of Termination Events is largely consistent between the Victorian and NSW Commercial Principles. Examples of Termination Events are:
There are a few differences between NSW and Victoria as to what constitutes a Termination Event, for example:
Differences in the Event of Default regime between NSW and Victoria
Typical Events of Default are:
The NSW specification of Events of Default is slightly stricter than in Victoria:
Cure periods for an Event of Default
Under both the NSW and Victorian regimes, the cure period for an Event of Default will be agreed at the time and incorporated into a cure plan. The Victorian Commercial Principles provide a mechanism by which this cure period can be extended provided that the private party:
NSW does not provide a mechanism for the extension of the cure periods. This can be explained by the different ways in which their respective project agreements provide for cure by financiers. In NSW, financiers have a separate and distinct cure period which operates outside of the project agreement.
Under the NSW model, where the Government has a right to terminate the project agreement and the relevant cure periods have elapsed, the financiers will then have a separate right to cure that default.
In Victoria, the rights to financiers to cure tend to co-exist with the cure rights in the Project Agreement – that is, if financiers want to cure they will need to step in and cure within the cure period provided in the Project Agreement itself. Therefore, it is more important to have a mechanism for extensions to the cure periods within the Victorian Project Agreements.
Persistent Breach regime
In NSW, a default may be subject to a Persistent Breach regime. There are two types of Persistent Breach outlined in the NSW Commercial Principles:
If another Persistent Breach occurs within the specified period, a Termination Event will result.
The purpose of a persistent breach regime is to pick up repeated Events of Default which may each be cured within the applicable cure period. It introduces a strong incentive for the private party to take appropriate steps to prevent them from occurring.
State Default
The final major difference in the termination regimes between the Victorian and NSW Commercial Principles is the introduction of a concept of State Default in NSW. In NSW, where:
Calculating Termination Payments
Termination Payments based on private party default
At a high level both the Victorian and NSW Commercial Principles adopt a market value approach to calculating payments. It is felt, at least in NSW, that the market value approach represents a balance between protecting Government’s interest and not imposing unreasonable deductions on the private party for its default.
Generally the method by which the termination payment is calculated in both the Victorian and NSW Commercial Principles is similar. Called the Estimated Fair Value, it is:
In both NSW and Victoria, where a liquid market exists, Government may tender out the unexpired term of the Project, as opposed to undertaking an Estimated Fair Value exercise. In such case the Termination Payment will be the capital sum paid by the successful tenderer less certain specified deductions. The rationale being that the best way to determine the market value of a project is to allow the market itself to determine that value, rather than try to approximate the value by using the calculation above.
What is a liquid market?
The Victorian Commercial Principles does not define a liquid market. In the past, NSW project documents have defined liquid market as there being at least two bidders (each capable of performing the project), in the market for PFP contracts or similar contracts for the provision of services, to ensure that the price that is likely to be achieved through a tender will be a suitable indicator of fair value.
This definition does not look at whether there are two bidders for the project in question, but generally two bidders who maybe capable of bidding for the project. The definition is drafted this way because:
Estimated Fair Value calculation
In calculating the Estimated Fair Value formula the cost of providing the services going forward is deducted. By doing this the termination payment takes into account scenarios where the termination event has occurred because the private party mis-priced or aggressively under-priced its bid.
By deducting the cost of rectification, the formula ties the amount of the Termination Payment to the condition of the asset, thereby arguably incentivising financiers to step in and rescue a project, as the ability of financiers to be repaid in full out of the Termination Payment may depend on the condition of the asset.
The New South Wales approach is to discount the Service Payments by the Base Case Weighted IRR[2] – what is essentially the weighted average cost of capital (WACC)[3].
The Victorian Commercial Principles adopts a different approach. It discounts the service payment by the higher of the base case equity return and the prevailing market rate of return. This means that its Termination Payment will be lower than under the NSW Commercial Principles as the equity return rate is greater than the weighted average cost of capital (because equity is more expensive).
It is likely that Victoria will re-think its position and adopt the NSW approach.
NSW prefers using the base case WACC as it will only use the estimated fair value approach where there is no liquid market, and in the absence of a liquid market it may be difficult to determine what the prevailing market rate of return is. From this calculation payment NSW Government will also deduct:
Calculating the Estimated Fair Value during the Construction Phase
The Victorian Commercial Principles applies the NPV approach to the Construction Phase too. NSW does not. During the Construction Phase the Termination Payment will be determined as the lower of:
The Net Present Value approach thus only applies in NSW during the Operations Phase. NSW has adopted this split approach because it was concerned that the NPV approach does not adequately take into account potential cost overruns during the construction phase and may, in some cases, lead to a windfall gain for the private party. Victoria may reconsider its position on this issue too.
Force Majeure Termination Payment
Generally the calculation of the Force Majeure (FM) Termination Payment Amount is the same between NSW and Victoria. Government will pay:
Victoria’s approach only differs in that it will not pay out any equity. As force majeure events are outside the control of both parties, the rationale is that both parties should share some of the pain. The Victorian Commercial Principles adopts the view that "sharing the pain" implies not paying out equity while NSW adopts the view that sharing the pain means the private party losing half of its equity (not all of the equity).
It should be noted that NSW has not adopted Victoria’s approach of calculating the termination payment on the basis of a private party default, if a private party default is subsisting at the time the project agreement is terminated for force majeure. It is unclear whether this will be acceptable to financiers; particularly as there is potential for their cure rights to be compromised if a force majeure termination event occurs before or during the financier’s step-in period.
Voluntary or State Default Termination Payment
Generally the calculation of Voluntary Termination Payment is the same under both the NSW and Victorian Commercial Principles. The Termination Payment will be equal to:
Again from the above amount Government will make similar deductions to those identified for default by the private party.
One key difference between the Victorian and NSW Commercial Principles is how they value the pay out of equity. NSW will value the payout of equity on the basis of the base case equity return while Victoria values it on the higher of the base case equity return or the market return. This means that in NSW, the private party gets all the upside of good performance, but none of the downside of bad performance.
Finally the Victorian Commercial Principles will, upon a Voluntary Termination, payout the greater of outstanding senior debt or the voluntary termination payment amount. NSW has not adopted this approach because it effectively means that the normal deductions NSW makes (for example, deductions for amounts owed by the private party to Government) cannot be set off against senior debt.
Thanks to Julian Gratiaen for his contribution to this article.
[1] PartnershipsVictoria: Standard Commercial Principles, Department of Treasury and Finance, Victoria and Working with Government: Risk Allocation and Commercial Principles, New South Wales Treasury (2007).[2] Base Case Weighted IRR means the average internal rate of return to both Equity and Debt providers, expressed as a percentage, that is stated in the Base Case. (This should be differentiated from the Base Case Equity IRR, which represents the internal rate of return only to Equity providers.) In the NSW Commercial Principles, the Base Case Weighted IRR is normally applied in relation to the calculation of Termination Payments.
[3] The term Weighted Average Cost of Capital (WACC) refers to the fact that firms use both equity and debt finance to purchase assets and the cost of each will generally be different. The cost of capital will be a weighted average of the cost of equity and debt, with the weights equal to the proportions of equity and debt in total capital, commonly known as the capital structure.
For further information, please contact John Shirbin.