10 July 2009
Key Points:
Carbon capture storage project proponents should carefully consider the location of their proposed project and the range of different environment and heritage assessments and approvals that may be required at an early stage in the planning process and allocate sufficient time and resources for this task.
All carbon capture and storage (CCS) projects will have a range of environment and health and safety risks associated with the capture, separation, transport, injection and storage phases that will need to be assessed and minimised. The Commonwealth Government and Victorian, Queensland and South Australia Governments have recently either varied existing petroleum legislation or enacted new standalone legislation to permit the storage of carbon dioxide in deep geological formations offshore (eg. depleted oil and gas reservoirs) and onshore (eg. unmineable coal seams onshore). This legislation regulates the risk of potential carbon dioxide leaks through a work plan or program that forms part of the authorisations which specify:
The Minister responsible for regulating each Act will need to consult with other relevant Ministers responsible for the environment and water in each jurisdiction where there may be potential environmental impacts. In South Australia, for example, a proponent must prepare an environmental impact report assessing the potential impact of its activities and a statement of environmental objectives for low, medium and high impacts of the project (see Petroleum Act 2000 (SA)).
In addition to CCS specific legislation, proponents will need to consider a range of other potentially relevant legislative instruments depending on the nature, scope and, most importantly, location of the project which may regulate:
This article focuses on the potential relevance of the other legislative instruments such as the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act) to carbon storage projects and the recently released Environmental Guidelines for Carbon Dioxide Capture and Geological Storage 2009 approved by the Environment Protection and Heritage Council and Ministerial Council on Mineral and Petroleum Resources Joint Officials Working Group which set out broad principles for assessing the environmental impact of CCS projects.
CCS Guidelines
A primary objective of the CCS Guidelines is to encourage national consistency and provide certainty for stakeholders regarding the application of current environmental regulatory processes for early CCS projects in relation to:
The CCS Guidelines envisage that the experience gleaned from early projects in the next decade will be used to develop best practice regulation. According to the CCS Guidelines, the level of assessment needed for a CCS project will hinge on the degree of environmental and community values that are impacted and proponents are strongly encouraged to consult with relevant authorities early in the planning process and be transparent in their dealings with regulators, the general public and local communities. The CCS Guidelines set out a number of broad guiding principles, including:
While the CCS Guidelines provide some generic overarching principles for environmental assessment, the real detail will be in applicable Acts and underlying regulations in the jurisdiction where the CCS project is located.
Potentially relevant environmental and heritage assessments
It is likely that not all environmental issues will be addressed by the project specific approval process under the relevant CCS legislation. CCS proponents may need to also undertake a range of environmental or heritage assessments under other Commonwealth or State legislation depending on the project's location. Of particular importance will be an assessment as to whether or not the EPBC Act (the Commonwealth Government’s central piece of environmental legislation) is applicable.
The EPBC Act provides a legal framework to protect and manage nationally and internationally important flora, fauna, ecological communities and heritage places — defined in the Act as matters of "national environmental significance". If a proponent is proposing to undertake any exploration or operational activities that will or are likely to have a significant impact on:
it must refer the activity to the Department of the Environment, Water, Heritage and the Arts (DEWHA) in accordance with the EPBC Act. This "referral" is then released to the public for comment and the Minister or his delegate will decide whether the likely environmental impacts of the activity are such that it should be assessed under the EPBC Act.
There are five different levels of assessment that DEWHA may undertake, depending on the significance of the activity and how much information is already available. DEWHA will make a recommendation to the Minister regarding whether or not the activity should proceed and any conditions that should be added to the approval. The Minister will consider the social and economic impacts of a project as well as the environmental impacts in determining whether or not to authorise an activity. DEWHA has developed an interactive database which is a useful tool for proponents requiring information on matters of national environmental significance. Proponents will also need to check the national heritage list and Commonwealth heritage list.
For projects in offshore areas, a proponent may also need EPBC Act permits if it is proposing to carry out activities (eg. seismic surveys) in a Commonwealth marine reserve or an area where whales are likely to be. In addition, a permit may be required if a proponent's activities could result in carbon dioxide being injected into the marine environment under the Environment Protection (Sea Dumping) Act 1981 or if the proponent needs to enter a historic shipwreck protection zone declared under the Historic Shipwrecks Act 1976.
In order to prioritise key conservation values in marine areas, the Commonwealth Government has embarked on a program of marine regional planning under the EPBC Act. Each plan will describe a region's key habitats, plants and animals; natural processes; human uses and benefits; and threats to the long-term ecological sustainability of the region. The plans will be a useful source of information for proponents as they will give details about the various statutory obligations under the EPBC Act that apply in the particular region.
For onshore projects, proponents will need to assess whether or not additional environmental assessment is required under environmental legislation in the relevant jurisdiction. Proponents should also carefully consider whether or not any proposed activities may have an impact on Indigenous heritage values and whether there are any native title claims or determinations under the Native Title Act 1993 or relevant State or Territory legislation. Even if an area is not covered by a native title determination or claim this does not necessarily mean that there are no Indigenous people asserting rights to an area. Aboriginal Land Councils, State heritage agencies and Aboriginal Affairs Departments, the National Native Title Tribunal, Native Title claimants and Prescribed Body Corporates under the Native Title Act are useful sources for proponents seeking to identify the relevant authorised and other Indigenous people with interests in a release area.
Conclusion
Proponents of CCS projects will have to navigate through a range of complex environmental assessment and approval regimes. The type and location of the project will be a critical factor in determining the degree of environmental and heritage assessment that is required. This process should be commenced at the planning stage of the CCS project as it is likely to be time consuming and require technical and legal input and consultation with a variety of different stakeholders.
For further information, please contact Claire Smith.